Crusoe Cancels $1.25B Boom Turbine Deal for AI Data Centers
Crusoe has terminated its $1.25 billion agreement to purchase 29 Boom Superpower gas turbines, just weeks after raising $3.9 billion in new funding. The cancellation, confirmed by Boom CEO Blake Scholl on X, comes before deliveries were set to begin in 2027. Boom now targets 250 MW of turbine deliveries to other sites next year and 1 GW by 2028, while Crusoe continues building its 1.2 GW Abilene campus for Oracle and OpenAI.
Executive Overview
Crusoe, the U.S. company specializing in AI data center construction, has officially terminated its partnership with Boom Supersonic to purchase 29 Superpower gas turbines valued at $1.25 billion. The announcement came via a post on X by Boom CEO Blake Scholl on Friday and was confirmed to TechCrunch by Crusoe. The decision follows Crusoe's recent $3.9 billion funding round and precedes the originally scheduled delivery start in 2027. Boom now aims to deliver approximately 250 MW of Superpower turbines to other sites next year and 1 GW by 2028. The cancellation represents a setback for Boom's ambitions to fund its Overture supersonic jet development through stationary power revenues.
📊 Official Data & Technical Specifications Sheet
| Technical Axis | Confirmed Official Data |
|---|---|
| 💰 Canceled Deal Value | $1.25 billion for 29 Superpower gas turbines |
| ⚡ Capacity per Turbine | 42 MW per Superpower turbine |
| 🏭 Crusoe's Latest Funding | $3.9 billion (raised recently before deal cancellation) |
| 💵 Boom's Previous Funding | $300 million (raised last year to commercialize stationary power business) |
| 🔧 Shared Components Ratio | 80% between stationary Superpower turbine and flying Symphony engine |
| 📅 Canceled Delivery Date | Deliveries were scheduled to begin in 2027 |
| 🎯 Boom's Alternative Targets | 250 MW to other sites in 2025, and 1 GW by 2028 |
| 🏢 Crusoe Data Centers | 1.2 GW in Abilene for Oracle and OpenAI (grid-powered), and 900 MW for Microsoft (on-site gas turbines) |
| 🌐 Platforms & Availability | Crusoe data centers in Abilene, Texas; Boom turbines targeted for multiple sites |
| 🛡️ Operational Security | Gas turbines for backup power at Oracle/OpenAI facility; on-site turbines for Microsoft facility |
| 🧠 Energy Context | Multi-source energy mix: grid, gas turbines, wind, solar, batteries |
| 🌍 Arab Region Support | No official announcement of expansion in the Arab region within this deal |
Deep-Dive Features & Architecture
Founded in 2018 as a Bitcoin mining company operating on natural gas flared from oil fields, Crusoe has transformed into one of the largest builders of AI data centers, including the massive Abilene campus in Texas that supplies computing power to OpenAI. Crusoe was the first customer for Boom's new stationary power plant business, signing an agreement to purchase 29 turbines from Boom's production line of 42 MW per unit, for a total value of $1.25 billion, with deliveries starting in 2027.
Blake Scholl, CEO of Boom, explained in his post on X that the turbines were no longer part of Crusoe's short-term core energy mix in Abilene, making the launch partnership illogical. He confirmed that Boom will deliver approximately 250 MW of Superpower turbines to other sites next year, targeting 1 GW by 2028. Andrew Schmidt, spokesperson for Crusoe, stated that the company builds AI factories from the energy up, selecting the appropriate power solutions for each site based on evolving needs, including turbines, wind, solar, batteries, and the grid.
The Superpower turbine shares approximately 80% of its components with the Symphony engine that Boom is developing for the Overture supersonic jet. Boom had raised $300 million last year, with the primary goal of commercializing its stationary power plant business, directing profits to fund Overture development.
Benchmark & Competitive Performance
Regarding the energy mix, Crusoe's first Abilene center, with 1.2 GW capacity for Oracle and OpenAI, relies on the electrical grid, with a gas turbine plant for backup power only. In contrast, a second center with 900 MW capacity for Microsoft is being built with on-site gas turbines. This dual approach highlights Crusoe's strategy of tailoring power solutions to each site's requirements, balancing grid reliability with on-site generation for energy-intensive AI workloads.
Boom's Superpower turbine, with its 42 MW capacity and 80% component commonality with the Symphony engine, represents a significant entry into the stationary power market. The canceled deal with Crusoe was a major validation of Boom's pivot to energy, and its loss underscores the challenges of scaling a new turbine business while simultaneously developing a supersonic aircraft.
Industry Impact & Enterprise Adoption
The cancellation of the $1.25 billion deal is a notable blow to Boom's ambitions to fund Overture development through stationary power revenues. However, Boom's revised targets of 250 MW in 2025 and 1 GW by 2028 indicate continued demand for its turbines from other data center operators and industrial customers. The AI data center boom is driving unprecedented demand for reliable, scalable power, and companies like Crusoe are aggressively securing diverse energy portfolios to support massive GPU clusters for customers like OpenAI, Oracle, and Microsoft.
Crusoe's $3.9 billion funding round, raised just weeks before the cancellation, provides ample capital to pursue alternative power strategies. The company's ability to pivot quickly reflects the dynamic nature of AI infrastructure development, where energy sourcing is as critical as compute hardware. As AI models grow in size and complexity, the race to secure power—whether from the grid, gas turbines, renewables, or batteries—will intensify, shaping the competitive landscape for data center providers.
Conclusion
The termination of the Crusoe-Boom turbine deal highlights the volatility and strategic recalibration underway in AI data center power procurement. While Boom loses a flagship customer, its revised delivery targets and ongoing Overture development keep its long-term vision intact. Crusoe, flush with $3.9 billion in new funding, remains focused on building flexible, multi-source energy solutions for its expanding AI factory portfolio. The episode underscores that in the AI era, power is the new currency, and adaptability is key to sustaining growth.
Media Source: TechCrunch AI | Fact Verification & Analysis: AI Tools Oasis
Frequently Asked Questions
The deal was valued at $1.25 billion for the purchase of 29 Superpower gas turbines, each with a capacity of 42 MW. Deliveries were scheduled to begin in 2027. The agreement was fully canceled, according to Boom CEO Blake Scholl.
Crusoe recently raised $3.9 billion. It operates a 1.2 GW data center in Abilene, Texas, dedicated to Oracle and OpenAI, powered by the grid, plus another 900 MW facility for Microsoft powered by on-site gas turbines.
Boom aims to deliver approximately 250 MW of Superpower turbines to other sites next year, with a target of 1 GW by 2028, according to CEO Blake Scholl on X.
The stationary Superpower turbine shares about 80% of its components with the Symphony engine that Boom is developing for the Overture supersonic jet.
Boom raised $300 million last year, primarily to commercialize its stationary power plant business, with profits directed toward funding the development of the Overture supersonic jet.

AI Tools Oasis Team